Hoteldevelopment

Moxy Little Havana

1420 SW 8th StMiami, FL • 154 keys

Value
$62.5M
NOI
$0
Revenue
$0
Health
72
01

Executive Summary

Sample briefing

Construction 65% complete; MEP change orders added $340K but contingency remains at 4.2%. Delivery moved to Q1 2027.

Top Positives
  1. 01Structure topped out
  2. 02Facade 82% installed
  3. 03Under GMP contingency
  4. 04Pre-lease pipeline building
  5. 05Debt facility fully committed
Top Concerns
  1. 01FF&E lead time slipping
  2. 02Two RFIs unresolved >30d
  3. 03Interior fit-out labor tight
  4. 04Miami-Dade permit backlog
  5. 05Rising insurance premium
Suggested Actions
  1. 01Accelerate FF&E procurement
  2. 02Weekly RFI review with GC
  3. 03Lock rate on construction loan draw
  4. 04Confirm FLSA labor plan
  5. 05Bid excess-liability early